Guide · Checklist

The shop fit-out checklist

Fifty-plus items across six stages — the same list an experienced project manager works through, in the order that avoids rework.

Home / /guides / Checklist
How to use it: work top to bottom. Do not start construction until the “Approvals” block is complete — that single discipline prevents most stop-work orders and insurance voidance.

Before you sign the lease

  • Confirm the permitted use in the lease and the planning approval
  • Get the landlord’s or centre’s fit-out guide in writing
  • Check available power, water, gas and grease riser capacity
  • Check floor loading and ceiling height
  • Confirm make-good obligations and after-hours access rules
  • Check trading hours and any exclusivity/competition clauses
  • Confirm whether the shopfront and signage are yours to change

Design and documentation

  • Measured survey of the tenancy
  • Layout with egress widths and accessible path of travel
  • Joinery drawings and finishes schedule
  • Mechanical, electrical, plumbing and fire drawings
  • Acoustic and odour assessment if food or late trading
  • Signage design within the planning exemption limits

Approvals

  • Engage a building surveyor / certifier
  • Lodge development consent if the use changes
  • Lodge building approval with documentation
  • Lodge plumbing permit and trade waste / grease trap consent
  • Apply for food business registration
  • Apply for liquor licence if applicable
  • Apply for footpath trading permit if seating outside
  • Check heritage or design overlay requirements

Procurement

  • Three itemised quotes compared line by line
  • Licence number verified with the regulator
  • Contract with scope, programme, variations and defects liability
  • Joinery and imported item lead times confirmed
  • Insurance certificates: public liability, workers comp, contract works

Construction

  • Site establishment, hoarding and skip permits
  • Demolition and make-safe; asbestos check if pre-2004
  • Services rough-in: electrical, plumbing, mechanical, fire
  • Framing, partitions and ceilings
  • Joinery install and shopfront
  • Finishes: floors, walls, tiling, painting
  • Signage install after approval

Inspections and handover

  • Rough-in inspections at the required stages
  • Final building inspection
  • Fire services certification and fire safety schedule
  • Food premises inspection
  • Liquor premises inspection
  • Occupation certificate issued
  • As-built drawings, warranties and O&M manuals handed over
  • Defects list agreed with a rectification period
Guidance only. Requirements vary by state, council and building classification. Confirm with your building surveyor or certifier.