What needs approval — and what doesn’t

A plain-English breakdown of every common fit-out work item, who signs it off, and the state-by-state differences that catch people out.

Home / Guides / Approvals

The one rule that decides everything

Approval isn’t about how much you’re spending — it’s about whether you change the use, the structure, the fire safety systems or the egress of the building.

If your fit-out touches none of those four, you can usually proceed with only landlord consent. Touch any one of them and you enter the approval system — building approval first, then occupation certificate before you trade. Change the use (office to café, retail to gym) and every state adds a planning or development consent in front of the building approval.

Worked example: a 120 m² retail tenancy refit with new joinery, paint and flooring needs no council approval in most states — just landlord sign-off. The same tenancy becoming a café needs development consent, a building approval for the exhaust and fire upgrade, a plumbing permit for the grease trap, trade waste consent and food registration. Same size, same budget order of magnitude, six approvals instead of none.

Work item matrix — approval or exempt

Use this as a first filter. Anything marked “approval required” needs a licensed practitioner and a paper trail; anything “usually exempt” still needs landlord consent and a check against the fire safety schedule.

Work itemApprovalWho signs offWhat to know
Repaint, new floor coverings, loose furnitureUsually exemptOnly landlord consentCosmetic finish changes are not building work in any state. Check lease obligations and centre guidelines.
New joinery — counters, shelving, displaysUsually exemptOften none; landlord consentFixed joinery that doesn’t alter egress, structure or fire systems is generally exempt. Keep exit paths clear.
Non-structural partition wallDependsPermit varies by stateExempt in most states if it doesn’t affect egress, fire compartments or services. Always check with a surveyor.
Structural alteration or new mezzanineApproval requiredBuilding approval requiredNeeds structural engineering, building approval and often a fire upgrade. Never proceed without approval.
New or altered shopfront / façadeApproval requiredBuilding + planning approvalFaçade changes usually trigger planning consent (heritage, character, signage) plus building approval for glazing and egress.
Change of use (office → café, retail → gym)Approval requiredDevelopment approval requiredThis is the big one. Every state requires development consent for a material change of use, then a building approval.
New commercial cooking / exhaust canopyApproval requiredBuilding approval + council conditionsMechanical ventilation, fire suppression, grease-laden discharge and odour/noise conditions all apply.
Grease trap or plumbing alterationsApproval requiredPlumbing permit + trade waste consentTwo separate approvals: the plumbing permit and the water authority’s trade waste consent.
Sprinkler, hydrant or fire panel changesApproval requiredBuilding approval + fire contractorFire services alterations require approval and licensed fire protection contractors; the fire safety schedule is updated.
Illuminated or projecting signageApproval requiredCouncil consent (may be exempt)Small fascia signs are often exempt; illuminated, projecting or heritage signs need consent and sometimes building approval.
Outdoor dining / footpath tradingApproval requiredCouncil permitSeparate footpath trading permit with furniture, insurance and clearance conditions.
Liquor licence / BYO authorisationApproval requiredState liquor authorityRuns parallel to building approval; the premises is inspected against licence conditions.
Food business registrationApproval requiredCouncil or health authorityRequired before opening for any business handling food — inspection of the completed fit-out.
Skip bin, hoarding or crane on streetApproval requiredCouncil permitStreet occupation permits are separate and time-limited.

State-by-state: who signs what

The work is national, the paperwork isn’t. This is the 2026 map of which authority handles which approval.

StateDevelopment / buildingFood premisesLiquorSignageFire
New South WalesDA or CDC (complying) + CC/OCCouncil notification (Food Act 2003)Liquor & Gaming NSWCouncil / exempt development rulesAFSS + fire safety schedule
VictoriaBuilding permit (RBS) + planning permit if use changesCouncil registration (Food Act 1984)VGCCCPlanning permit for major signageESM schedule + annual report
QueenslandDevelopment approval (council) + building approval (certifier) + Form 21Council food business licence (Food Act 2006)OLGRCouncil advertising device approvalFire safety management schedule
Western AustraliaCouncil development approval + building permitLocal government registration (Food Act 2008)Racing, Gaming & LiquorCouncil planning approvalDFES + fire safety schedule
South AustraliaPlanSA development approval + building consentCouncil notification (Food Act 2001)Consumer & Business ServicesPlanSA / Planning & Design CodeMFS/CFS + essential services
TasmaniaCouncil planning permit + building permitCouncil registration (Food Act 2003)CBOS Liquor & GamingCouncil planning approvalTFS + fire safety schedule
ACTEPSDD DA + Crown lease variation + building approvalACT Health Protection Service (Food Act 2001)Access CanberraDevelopment approvalACT Fire & Rescue
Northern TerritoryDCA development consent + building permitNT Health / council (Food Act 2004)NT Liquor CommissionCouncil (e.g. City of Darwin)NT Fire & Rescue

Full detail per state, including licence thresholds and local gotchas: state guides.

What’s usually exempt (but still needs care)

  • Paint, carpet, vinyl, loose furniture — cosmetic only, no approval in any state.
  • Joinery and counters — exempt unless they obstruct an exit path or reduce egress width.
  • Lighting and power swaps — like-for-like electrical work by a licensed electrician; new circuits need a certificate of electrical compliance.
  • Small fascia signage — often exempt under planning codes, but heritage items and illuminated signs are not.
  • Non-structural partitions — exempt in most states if they don’t affect fire compartments, egress or services. Get written confirmation from a surveyor; “the builder said it was fine” is not a defence.

What’s never optional

  • Structural work — engineer’s design plus building approval.
  • Fire systems — sprinklers, hydrants, detection, exit signage, fire doors.
  • Access — AS 1428.1 / NCC access compliance for new work.
  • Plumbing and trade waste — licensed plumber plus water authority consent.
  • Food premises — registration before opening, in every state.
  • Liquor — licence before trading alcohol.
  • Occupation certificate — opening before it’s issued is a compliance breach and can void insurance.

The approval sequence that avoids blowouts

Week 0

Read the lease and the centre guide

Make-good obligations, permitted use, trading hours and landlord approval process. This is where most budget surprises are already written down.

Week 1

Confirm the planning status of the use

Does the current approval permit your use? If not, a development application is on the critical path and everything else waits.

Week 1–2

Engage the building surveyor or certifier

They tell you which approvals are actually triggered — councils and certifiers can disagree, and the certifier is the one who signs your occupation certificate.

Week 2–4

Lodge plumbing, trade waste and food applications in parallel

These have their own queues and don’t depend on the building approval being issued.

Week 3–8

Build under the approved documentation

Any variation goes back through the certifier. Unapproved variations are the most common cause of a failed final inspection.

Handover

Inspections, certificates, then open

Final inspection, occupation certificate, fire safety schedule in hand, food and liquor inspections booked.

Approval FAQs

Can my landlord approve the fit-out instead of the council?
No. Landlord consent is a contractual permission, not a statutory one. A centre manager’s approval does not replace a building approval or development consent — but a centre can refuse work that the council would allow.
What happens if I open before the occupation certificate?
It’s a breach of building law, it can void your public liability insurance, and councils can issue notices to stop using the premises. Fire authorities can close a premises that doesn’t have a valid fire safety statement.
Do I need a certifier if I’m only doing joinery?
Probably not — but confirm it in writing. The test is whether the work affects egress, fire, structure or services. A certifier’s one-line email is cheap insurance.
How long do approvals take?
Building approval: 2–6 weeks for a straightforward retail fit-out. Development consent for a change of use: 6 weeks to 6 months depending on state and whether it’s assessable or code-assessable. Food registration: 2–4 weeks including inspection.
Guidance only. Approval triggers vary by site, building classification and council. Confirm with your building surveyor/certifier before committing to a programme.